Study IDs trouble areas, aims to speed up construction projects

Date:
September 5, 2013
Source:
North Carolina State University
Summary:
Researchers have identified factors that cause construction site managers to schedule more time than necessary for specific tasks. Understanding these factors and whether they can be reduced or eliminated could help the industry complete construction projects more quickly.

Even small time buffers can lead to thousands of hours of delays on construction projects.
Credit: NC State University

Research from North Carolina State University identified factors that cause construction site managers to schedule more time than necessary for specific tasks. Understanding these factors and whether they can be reduced or eliminated could help the industry complete construction projects more quickly.

At issue is a construction planning concept called a time buffer. A time buffer is the difference between how long it should take to accomplish a task based on optimum productivity, and how long you think it will take in the real world. On any job, things can go wrong; bad weather or broken equipment can delay completion of a task. To account for these unforeseen events, construction foremen add time buffers into their schedules.

For example, if the optimum time for a task is three days, and a foreman adds one day of buffer time, the foreman tells his supervisor and project manager that the task will take four days.

"This is important, because construction projects -- like building a school or hospital -- can consist of thousands of tasks," says Dr. Min Liu, an assistant professor of civil, construction and environmental engineering at NC State and senior author of a paper on the research. "If every site manager builds a small buffer into every task, it can come to thousands of hours.

"Time buffers are contingencies that are built in, in case something goes wrong -- but there is something called student syndrome," Liu says. "Student syndrome says a student won't do his homework until the night before it is due. Similarly, if a foreman thinks a task will take three days, but allots four days to do the work, the work is more likely to take the full four days. It's similar to Parkinson's Law, which says that a task will fill the amount of time allotted to complete it.

"We did this study to better understand how people determine when to add time buffers, and the length of those time buffers," Liu says. "This helps us determine how much of a time buffer is actually necessary, and will help us find ways to minimize wasted time in construction projects."

The researchers analyzed survey results of 180 construction industry professionals from across the United States. They found a number of factors that contribute to time buffers.

Some factors are frequent contributors to time buffers, but do not increase the time buffer by very much. An example of this is a desire to protect the reputation of the construction company. Some factors occur infrequently, but can significantly lengthen a time buffer. An example of this is a delay in getting a necessary permit. And some factors are both frequent and significant. For example, if the task is part of a complex project -- like a laboratory facility -- that complexity often leads to lengthy time buffers.

"Project managers can use the factors we've identified to prioritize their review of construction tasks and target issues related to time buffers," Liu says. "For example, managers can pay particular attention to factors that are most likely to result in lengthy time buffers in order to determine if those time buffers are necessary or can be reduced."


Story Source:

The above story is based on materials provided by North Carolina State University. Note: Materials may be edited for content and length.


Journal Reference:

  1. Marion M. Russell, Gregory Howell, Simon M. Hsiang, Min Liu. Application of Time Buffers to Construction Project Task Durations. Journal of Construction Engineering and Management, 2013; 04013008 DOI: 10.1061/(ASCE)CO.1943-7862.0000735

Cite This Page:

North Carolina State University. "Study IDs trouble areas, aims to speed up construction projects." ScienceDaily. ScienceDaily, 5 September 2013. <www.sciencedaily.com/releases/2013/09/130905113714.htm>.
North Carolina State University. (2013, September 5). Study IDs trouble areas, aims to speed up construction projects. ScienceDaily. Retrieved September 2, 2014 from www.sciencedaily.com/releases/2013/09/130905113714.htm
North Carolina State University. "Study IDs trouble areas, aims to speed up construction projects." ScienceDaily. www.sciencedaily.com/releases/2013/09/130905113714.htm (accessed September 2, 2014).

Share This




More Matter & Energy News

Tuesday, September 2, 2014

Featured Research

from universities, journals, and other organizations


Featured Videos

from AP, Reuters, AFP, and other news services

Google Teases India Event, Possible Android One Reveal

Google Teases India Event, Possible Android One Reveal

Newsy (Sep. 1, 2014) Google has announced a Sept. 15 event in India during which they're expected to reveal their Android One phones. Video provided by Newsy
Powered by NewsLook.com
Australian Airlines Relax Phone Ban Too

Australian Airlines Relax Phone Ban Too

Reuters - Business Video Online (Aug. 26, 2014) Qantas and Virgin say passengers can use their smartphones and tablets throughout flights after a regulator relaxed a ban on electronic devices during take-off and landing. As Hayley Platt reports the move comes as the two domestic rivals are expected to post annual net losses later this week. Video provided by Reuters
Powered by NewsLook.com
Hurricane Marie Brings Big Waves to California Coast

Hurricane Marie Brings Big Waves to California Coast

Reuters - US Online Video (Aug. 26, 2014) Huge waves generated by Hurricane Marie hit the Southern California coast. Rough Cut (no reporter narration). Video provided by Reuters
Powered by NewsLook.com
Chinese Researchers Might Be Creating Supersonic Submarine

Chinese Researchers Might Be Creating Supersonic Submarine

Newsy (Aug. 26, 2014) Chinese researchers have expanded on Cold War-era tech and are closer to building a submarine that could reach the speed of sound. Video provided by Newsy
Powered by NewsLook.com

Search ScienceDaily

Number of stories in archives: 140,361

Find with keyword(s):
Enter a keyword or phrase to search ScienceDaily for related topics and research stories.

Save/Print:
Share:

Breaking News:
from the past week

In Other News

... from NewsDaily.com

Science News

Health News

Environment News

Technology News



Save/Print:
Share:

Free Subscriptions


Get the latest science news with ScienceDaily's free email newsletters, updated daily and weekly. Or view hourly updated newsfeeds in your RSS reader:

Get Social & Mobile


Keep up to date with the latest news from ScienceDaily via social networks and mobile apps:

Have Feedback?


Tell us what you think of ScienceDaily -- we welcome both positive and negative comments. Have any problems using the site? Questions?
Mobile: iPhone Android Web
Follow: Facebook Twitter Google+
Subscribe: RSS Feeds Email Newsletters
Latest Headlines Health & Medicine Mind & Brain Space & Time Matter & Energy Computers & Math Plants & Animals Earth & Climate Fossils & Ruins